Overview
This error appears when a user attempts to complete an assessment with a date that is earlier than the learner’s Onefile start date. The system prevents completion until the assessment date is corrected.
User Roles
This issue can be resolved by:
- The user who started the assessment
- Centre Manager
How to Resolve the Issue (Assessment Owner)
The user who originally started the assessment can update the date using the steps below:
- Open the Assessment.
- Change the Assessment Date to a date that is on or after the learner’s Onefile start date (shown in the error message).
- Click Save and Quit.
- Reopen the assessment.
- Check that the date has updated successfully.
- Complete the assessment.
How to Resolve the Issue (Centre Manager)
Centre Managers can override and resolve multiple affected assessments:
- Log in as a Centre Manager.
- Click the banner at the top of the page indicating there are date conflicts.
- Click Resolve next to each learner and assessment listed.
This will correct the date conflict and allow assessments to be signed.
Tips & Notes
- The learner’s Onefile start date is set within their Episode — assessment dates cannot precede it.
- If the banner does not appear, refresh the page or ensure you have Centre Manager permissions.
- Historical assessments imported from other systems may require manual correction.
Terminology
The terminology used in this article may differ depending on your Centre’s configuration.